Funk’s Auto Body:

- This facility has all the high-tech tools needed for automotive frame and body repairs.
Description:
The owner’s requirements were to have a facility that would set new industry standards for auto body precision and shop technicians’ comfort. Design parameters for a dust-free environment, with a warm floor and bright lighting levels were important. Three Way Builders Ltd. utilized a concrete floor with in-floor heating pipes, and applied surface hardeners and scalers for durability. Under-floor ventilation and airflow pits were installed under the two paint booths.
The economical pre-engineered steel superstructure features full pre-finished metal liners on the walls and ceiling for ease of cleaning. Extra precautions were taken to ensure a dust-free office, including separate air distribution and the construction of an air-tight demising wall.
Statistics:
| Owner: | Clem Chaput |
| Method: | Design-Build, Contract |
| Total Area: | 10,800 sq.ft. (1003 m²) |
| Design: | September 1998 to October 1998 |
| Construction: | November 4, 1998 to May 21, 1999 |
| Comments: | A functional and attractive facility. |