Rural Municipality of Hanover Office Building
Owner: Rural Municipality of Hanover Method: Construction Management Total Area: Construction Management 8500 sq. ft. (790 m²) Design: Ron’s Drafting, L.L. Riding Engineering Ltd. Construction: June 20, 2000 to February 15, 2001 -
Day Star Band Office
Owner: Day Star First Nation Method: Design-Build Total Area: 12,412 sq. ft. (1153 m²) Design: Owner’s representatives, Three Way Builders Ltd., L.L. Riding Engineering, Nova Three Engineering Construction: October 9, 1999 to April 10, 2000 -
Ste Anne Co-op Bulk Petroleum Station
Owner: Ste. Anne Co-op Ltd. Method: Design-Build Total Area: 11,500 sq. ft. (1068 m²) Design: February 1998 to April 1998 Construction: April 16, 1998 to September 17, 1998 Comments: Special regulatory compliance met. Occupancy on schedule.